Health Secretary Edwin Mercado (2nd from left), Public Works Secretary Giovanni “Banoy” Lopez (2nd from right), and Transportation Secretary Vince Dizon (right) inspect the ongoing construction of new facilities at the National Kidney and Transplant Institute and the Philippine Cancer Center on Tuesday, Nov. 17. The facilities are targeted to begin operations between late 2027 and early 2028. —Photo by Chelsy Claire Perez
New facilities at the National Kidney and Transplant Institute (NKTI) and the Philippine Cancer Center (PCC) are expected to begin operations by late 2027 to early 2028, with the projects now in the third phase of construction, government officials said on Tuesday.
“We’re challenging our contractor to see if we can finish it by the end of 2027. But the most likely is the first quarter of 2028,” Health Secretary Edwin Mercado said.
The 12-story extension will house outpatient dialysis centers, an outpatient surgery center with four operating rooms, vascular access services for dialysis patients and additional clinics and offices.
The new dialysis facility will have 200 hemodialysis machines, which can accommodate around 600 patients across three shifts, Mercado said.
Catch-up for delays
Public Works Secretary Giovanni Lopez said the NKTI and PCC projects had experienced construction delays but were now being covered by catch-up plans.
PCC’s first five floors are targeted to become operational by late 2027 to the first quarter of 2028.
Mercado said these floors would house chemotherapy facilities, laboratories and a genomic center that would support precision medicine by helping doctors identify cancer treatments suited to individual patients.