Budget for multipurpose buildings draws scrutiny
Sen. Panfilo Lacson on Saturday questioned the justifications raised by proponents of the construction of more multipurpose buildings (MPBs), pointing out that these had been unequally distributed around the country over the past 14 years.
He cited the disparity in their locations, saying that most of these were built in high-income cities and municipalities rather than in poorer areas.
Lacson raised the issue as the Senate concluded the final day of its six-day marathon deliberations on the proposed P7.2-trillion national budget for 2027 in the wee hours of Saturday.
Critics have described allocations for MPBs as a new form of pork barrel, in the same way that the flood control project kickbacks replaced the now outlawed congressional Priority Development Assistance Fund.
Citing Department of Public Works and Highways (DPWH) data from 2012 to 2026, Lacson said the government spent P760 billion on 79,816 MPBs across the country, each one costing an average of P9.5 million.
The House General Appropriations Bill had listed more than 5,000 new MPB projects, which the Senate cut to roughly 1,400.
A 2026 local budget circular from the Department of Budget and Management defined MPBs as “fully enclosed structures built for permanent use” by the local government. These include health centers, sports stadiums, community centers, day care centers and public markets.
Surprising distribution
They are used for temporary shelters during natural calamities, aid distribution, sports, village assemblies and meetings, polling places, skills training and local cultural programs.
Lacson said that out of more than 79,000 MPBs in the 2012-2026 period, the first-class local government units (LGUs) accounted for 53,865, the second-class LGUs 10,671, the third-class LGUs 8,167, the fourth-class LGUs 5,229 and the fifth-class LGUs 976. The income classes of the remaining 908 MPBs were unidentified.
He said that 67.5 percent of the funding went to first-class cities and municipalities and “the poorest of the poorest got a measly 1.2 percent.”
Lacson said such distribution of MPBs was surprising and that he did not believe more MPBs were needed because the poorer areas of the country never received any.
The senator gave examples of the disparity in the distribution of MPBs during the past 14 years. He said 1,440 MPBs worth P31.5 billion were built in Quezon City, one of the highly urbanized and prosperous cities in the National Capital Region. There were 318 in Taguig City (P16.4 billion); 609 in Manila (P12.4 billion); 514 in Mandaluyong City (P11.5 billion); and 784 in Lipa City, Batangas (P11.2 billion).
Per municipality, the highest funding for MPBs went to Daraga, Albay, with 135 buildings worth P3.3 billion; 84 in Palo Leyte (P2.98 billion); 43 in Pili, Camarines Sur (P2.32 billion); 150 in Bocaue, Bulacan (P2.1 billion); and 184 in San Jose, Batangas (P2.07 billion).
Lacson said the disparity persisted in the Senate version of the proposed 2027 budget, with first-class cities still getting a large chunk of the MPB allocations.
In the Senate version of the budget for the DPWH, P54 billion was allocated for MPBs—P18.6 billion for 113 cities and P35.46 billion for 71 municipalities. The first-class cities were allocated P14.52 billion, or 78.1 percent of the total for city MPBs. No MPB funding was allocated to any fifth-class city.
The same pattern of distribution was observed among 849 municipalities, where 66 percent of the P35.46-billion funding was allocated to those classified as first class, while only 1.6 percent went to fifth-class municipalities.
“I think we should do some rethinking because after looking at the past data, we’re just repeating it, we’re just following the pattern. It’s more of the same, so we’re wasting [money],” Lacson said.
Watchdog’s findings
Senate finance committee chair Sen. JV Ejercito said, quoting Public Works Secretary Giovanni “Banoy” Lopez, the agency would “look into how they will prioritize fifth- and fourth-class municipalities.”
The budget watchdog People’s Budget Coalition (PBC) said in a statement on Friday that the Senate finance committee reduced funding for MPBs by P28.1 billion from the P83.7 billion approved by the House of Representatives.
The amount, however, remains P14.6 billion higher than the P41 billion originally proposed under the National Expenditure Program (NEP).
Funding for access roads to these buildings was likewise reduced by P24.3 billion to P110.7 billion, bringing the combined allocation for MPBs and access roads to P166.3 billion, still P19.6 billion above the NEP.
In a Facebook post last October, AJ Montesa, PBC co-convenor, said there were two “politicized” lump-sum items in the DPWH budget that some lawmakers were allegedly “feasting on”—the MPBs and the access roads.
PBC had questioned some P170 billion in additional allocations for multipurpose buildings and local roads, citing concerns over the necessity of the projects and possible irregularities.
In 2025, Mamamayang Liberal Rep. Leila de Lima and other critics flagged MPBs that were given identical P50-million allocations.
Biz groups also alarmed
Over 30 business and civil society groups last month also questioned the basis of many of these projects, which they said “appear as lump sums for multipurpose buildings and access and bypass roads, without published project lists or named proponents.”
On Friday, PBC cited earlier findings by Lacson, who flagged at least 30 suspected ghost MPBs and identified flood control projects that had been funded two or three times since 2024.
It urged senators to remove these projects during the period of amendments, along with other infrastructure projects lacking the required supporting documents or a named proponent.
According to the PBC, the allocations vulnerable to political patronage declined from P209.6 billion in the House version to P161.5 billion in the Senate committee report, still P21.4 billion above the NEP.
Among these allocations are P48.2 billion for the Assistance to Individuals in Crisis Situation program, P19 billion for the government’s emergency employment program and P41.6 billion in financial assistance to local government units.
“The cleanup isn’t over. As long as assistance is coursed through politicians’ referral letters, there is still pork in the budget,” Montesa said.
The coalition urged senators to restore these allocations to their NEP levels and redirect funds toward programs with established eligibility requirements, including the Pantawid Pamilyang Pilipino Program, tertiary education subsidies and crop insurance.
Citing instances in which Senate budget reforms were reversed during previous bicameral deliberations, PBC urged both chambers of Congress to adopt a joint resolution guaranteeing livestreamed proceedings, the presence of civil society representatives and journalists, and the publication of transcripts and a detailed breakdown of amendments before ratification. —WITH REPORTS FROM DIANNE SAMPANG AND INQUIRER RESEARCH
******
Get real-time news updates: inqnews.net/inqviber